Oxley Highway to Kundabung (OH2Ku) concrete paving update

Presentation by Cameron Peace on OH2Ku from Sydney Forum 29 October 2018

Project Background
Roads & Maritime Services 3
Pacific Highway Upgrade – Oxley Highway to Kundabung (OH2Ku)
The D&C contract for OH2Ku awarded April 2014
24km project, 110km/h dual carriageway
Completed March 2018 (18km section opened November 2017)

Project Background
Pacific Highway Upgrade – OH2Ku
2 mainline concrete pavers and 1 shoulder paver
1 Onsite concrete batch plant
160,000m3 of concrete in pavement
Two million cubic metres of earthworks
262 full-time workers
Contractor: Lendlease
Designer: Aurecon / PB
Project Verifier: Davis Langdon
Project/Contract Management: RMS