How to Replace Airfield Pavements in Under 6 Hours

Presentation by Al Mandowi - How to Replace Airfield Pavements in Under 6 Hours from ASCP Online Forum 16 June 2020

Nouas "Nate" Al Mandowi presents on ultra high efficiency rapid airfield pavement slab replacements. A case study of a project involving 23 slab replacements in 6-hour windows at Melbourne Airport in a critical highly trafficked taxiway.

The process of the project is outlined including, design, preparation, , demotion and excavation, subgrade preparation, joint preparation, rapid-set volumetric concrete mixing and placement techniques and a summary of the results.

Back to Resources